/ Terminal 1 Public Market Progress on Track

default
default

September 21, 2026

POV from middle of river looking north at the shoreline. A small barge with two lift booms floats in the river in front of a wide dock that is under construction. Two large cranes sit in the middle of the photo. Various construction materials and vehicles are on the shore in the construction area. Various high rise buildings create the backdrop to the photo. Blue skies with no clouds.
Construction activity continues on the brand new T1dock during July 2026.

Things are taking shape over the waterfront at Terminal 1.

The vision of an iconic public market in Vancouver over the Columbia River remains in sight for the Port of Vancouver USA. To reach that goal, replacing the century-old dock was an essential first step. Commuters on I-5 and visitors to the waterfront have likely noticed that the new dock is nearing completion.

The public market project has progressed at a pace dictated by in-water work windows – four-month portions of the year when state and federal agencies allow construction within the Columbia River.  

Beginning in 2023 by removing the old dock and its over 1,000 creosote wooden pilings, making the shore more earthquake-proof, improving fish habitat on the river floor and now installing the dock itself, the port has made the most of these October-through-January windows each year.

POV birds eye view in the Columbia River looking northeast at Terminal 1. A small dock with landscaping and pathways and a floating dock for boats sits in the center of the photo. To the east of that dock is an empty space where a dock used to be. Construction equipment is on the shoreline and along the riverbank. Three new high-rise buildings are on the shore behind the construction area. Cloudy skies with a very slight view of Mt. Saint Helens in the background.
Terminal 1 in late 2024 with the century-old T1 dock removed. Crews took the opportunity to make the bare shoreline more stable in the event of earthquake activity.

Since work once again shifted above the river in February 2026, crews have installed pile caps on the dock, temporary supports and precast concrete deck panels. They’re also preparing for the next in-water work window that begins October 1. Crews will be ready to finish dock and pile elements, place expansion joint plates and install electrical and utility infrastructure under the dock.

As that work progresses, installation of the additional steel piles and fenders will also take place. The port anticipates river cruises will resume visiting Vancouver in future years, so these improvements will help protect the dock when these vessels tie up.

POV birds eye view in the Columbia River looking north at a long, aged dock. a single new high-rise building sits behind the dock on the shoreline. some fresh mulch dots the landscaping of a new dock area to the left of the aged dock. On the aged dock there is rubble from a torn down building. Blue skies with hints of clouds. Mt. Saint Helens can be seen in the distance in the middle of the photo.
In May 2022, the old T1 dock was still in place. Engineering studies found the old structure was not sufficient to support the planned 40,000 sq. ft. public market.

The port will also be working diligently to restore the popular Renaissance Trail adjacent to the AC Hotel for pedestrians. The Terminal 1 portion of the trail will remain open throughout construction, although those strolling through will have to continue navigating a narrower pathway for a few more months to safely accommodate construction activity.

Crews will take other steps to maximize public safety and minimize sound disruptions while this work continues. For instance, visual barriers will remain in place along construction fencing to protect the public from welding arc-flash that can cause damage to eyes, crane operations and heavy material movement, as well as debris and dust.

The port plans to use a vibratory method to install the steel piles, rather than the noisier impact hammering method.  

Once the new dock is complete, work will shift toward developing and constructing the 40,000 square foot public market, with an anticipated opening in 2030. The details of the public market are still under design, though the port plans to have updated drawings to share with the public in the coming months.

Whether walking the Renaissance Trail, perusing the area’s history at Vancouver Landing, taking in views from the Launch or visiting the future public market, the birthplace of the port remains poised to become a premier destination for locals and visitors alike.

Timeline for Terminal 1 public market

2026-2027: From October through January, crews will install deck elements, pile caps, electrical and utility infrastructure and a protective fendering system. This work signals the completion of the T1 dock.

2028 –2030 (estimated): Construction of the public market.